The IT critical path for opening a restaurant, hotel or club

A week-by-week IT timeline for opening a restaurant, hotel or club, from circuit lead times and cabling first fix to soft launch and day-one support.

7 min readBy the MicroNet Global team

IT for a new venue opening sits on a critical path of roughly six months, and the leased line is almost always the longest lead item on it. MicroNet Global, a hospitality IT specialist with 550+ projects delivered across 15+ countries, plans openings backwards from the first service so connectivity, cabling and systems are live before staff arrive.

The item that most often delays an opening is the least glamorous one. A fibre order placed in week eight instead of week twenty-four is the reason a venue opens on a 5G router, taking cards slowly, with a manager apologising to a queue.

What is the IT critical path for a venue opening?

The IT critical path is the sequence of technology tasks whose dates cannot slip without moving opening day. It runs from site survey through circuit ordering, comms room agreement, containment and cabling, hardware procurement, systems build, payment onboarding, testing and soft launch, to day-one support and handover. Every other IT task can flex around it; these cannot.

The circuit is the problem, and it is ordered too late

A business-grade leased line is not a broadband order. It can require a survey, a landlord wayleave, civils works, and a delivery window measured in months. On a shell-and-core fit-out the address may not exist in the carrier's database yet, which adds weeks before anyone has picked up a spade.

IT is usually engaged after the lease is signed and the designer is already drawing, by which point the circuit has to be squeezed into whatever time remains. The honest response is not optimism; it is ordering on day one and building a fallback in parallel.

That fallback has to be real. Bonded 4G/5G with a proper router and a tested failover configuration will get a venue trading, but it will not comfortably carry full guest Wi-Fi, back-of-house video and a busy card estate at once. [[Networking, Wi-Fi and connectivity]{.underline}](about:blank) design should include the day-one degraded mode, not just the finished state.

Where IT sits in the construction programme

IT is downstream of the landlord, the main contractor, the M&E contractor and the designer. Very little is achievable by the IT team acting alone, which is why a venue opening is as much programme management as engineering.

Two decisions have to be made before walls go up. The first is the comms room location: central enough for cable runs to reach, away from kitchen heat and wet areas, lockable, with space to work in front of the rack. The second is power and cooling to that room, an M&E line item that has to be in their drawings rather than a request after commissioning.

The cabling follows the contractor's first fix and second fix windows, when ceilings and walls are open. Miss that and the choice is chasing finished plasterboard or running trunking across a designed interior. Neither conversation with a designer ends well.

The week-by-week critical path

The table below suits a mid-size restaurant or boutique property. A hotel with a full PMS, door locks and in-room entertainment needs the front end stretched. The dependencies do not change.

Weeks beforeWorkstreamDepends onRisk if late
26--24Site survey, requirements, IT budget and design briefLease signed, concept drawingsEvery downstream task compresses into the final month
24--20Connectivity ordered: primary circuit plus backup pathConfirmed trading address, landlord wayleaveOpening on mobile broadband with restricted service
20--16Comms room location, power and cooling agreed; containment and cabling design issuedM&E drawings, contractor programmeRemedial works, no cooling, kit in a cupboard
16--12Hardware ordered; PMS and EPOS contracts signedDesign sign-off, purchase order approvedStock lead times land after the fit-out finishes
12--8First fix: containment, cable pulls, back boxes, comms room powerContractor's first fix windowable chased into finished walls at your cost
8--6Payment terminals ordered; merchant onboarding startedMerchant ID, acquirer due diligenceTerminals on site with no live merchant account
6--4Second fix: rack, switches, access points, terminations and testingPower on, room clean and dryTrained staff arrive to boxes, not a network
4--3PMS/EPOS build, menu configuration, interface testingMenus signed off by operationsPricing errors and failed postings during service
3--2Network build tested end to end; Wi-Fi validated; devices enrolledCircuit liveWi-Fi rebuilt while the venue is trading
2--1Staff training, friends and family, soft launch as load testAll systems liveThe first genuine load test is paying guests
1--0Snagging, day-one support plan, on-site cover confirmedSnag list closedOpening-week faults with no named owner
+1 to +4Handover to business as usual: as-builts, asset register, SLA startDocumentation completeThe service desk inherits an undocumented site

Procurement lead times nobody budgets for

Three lead times catch operators repeatedly. Network hardware and EPOS terminals can carry long supply windows depending on model and vendor. Payment terminals depend on merchant onboarding, a compliance process with its own timetable and no interest in your opening date. PMS and EPOS build slots are booked in vendor calendars weeks ahead.

Menu configuration is the quietly enormous one. Someone has to build every dish, modifier, tax rate, course, printer route and discount rule, then test it. If the menu is not signed off three weeks out, that work happens the night before opening, and the [[integration points between PMS and EPOS]{.underline}](about:blank) are exactly where untested configuration breaks.

The soft launch is a load test, not a rehearsal dinner

Friends and family is the only chance to put real load on the systems before revenue depends on them. Run every card type through the terminals, including refunds and tips. Push the Wi-Fi with a full room of devices. Fire a full service through the kitchen printers and screens at once. Then fix every fault before the doors open properly.

Pre-opening is also when the support relationship starts. Day one wants an engineer on site, not a phone number. MicroNet Global's [[IT project management and delivery]{.underline}](about:blank) teams have run this pattern on openings including [[Ned's Club Washington DC]{.underline}](about:blank) and [[Swingers Las Vegas]{.underline}](about:blank), staying close through the first trading weeks rather than handing over at practical completion.

The handover that gets missed

Openings end untidily. The project team drifts away, the general manager is firefighting, and nobody formally transfers the site into support. Months later a switch fails and the service desk has no rack diagram, no asset register and no idea which VLAN the payment terminals sit on.

A proper handover is a short, boring document set: as-built cabling records, rack and port schedules, IP addressing, device inventory with serials and warranty dates, vendor references, admin credentials in the password vault, and a written start date for the support agreement. Agree it as a project deliverable with a sign-off, or it will not happen. Operators opening several [[restaurant and bar sites]{.underline}](about:blank) a year should make that pack a standard template, so site twelve looks like site one.

Frequently asked questions

Order it as soon as the lease is signed, ideally 24 weeks before opening. A business leased line can require a survey, a landlord wayleave and possible civils works, and any of those can add months. Order the primary circuit and a backup path at the same time, so a delayed install does not become a day-one trading problem.

Written by the MicroNet Global team. If you are working through any of this for your own estate, the specialists here are happy to talk it through.

Keep reading

Related insights

All insights
New openings6 min read

The technology checklist for a new hospitality opening

The questions operators should answer before the opening team arrives on site, from connectivity and suppliers to handover and live support.

Read article
Managed IT5 min read

Why hospitality needs a different IT support model

Hospitality does not operate in office hours. A useful support model is built around service, sites and the commercial cost of disruption.

Read article
Cyber security7 min read

A practical guide to hospitality cyber security

A plain-English starting point for protecting guest data, payment systems and the people who keep venues running.

Read article
Managed IT7 min read

What hotel IT support actually covers, and what it doesn't

What hotel IT support covers: systems in scope, who owns the PMS and door locks, contract tiers, exclusions and how response targets really work.

Read article
Managed IT7 min read

Why PMS and EPOS integrations break, and how to catch it early

Why PMS and EPOS integrations fail: stopped interface services, expired certificates, room status and API changes, and the checks that catch silent errors.

Read article
Managed IT7 min read

In-house IT team or hospitality IT partner: an honest comparison

In-house IT team or outsourced hospitality IT partner? An even-handed comparison of cover, cost, breadth, openings and the co-managed middle ground.

Read article
Networks & Wi-Fi7 min read

Why guest Wi-Fi generates complaints, and how to design it out

Why guest Wi-Fi draws complaints in hotels and restaurants, and how to design it out --- surveys, AP placement, captive portals, segmentation and peak load.

Read article
Networks & Wi-Fi7 min read

Wi-Fi 7 and the 6 GHz band: what actually changed for venues in 2026

Ofcom opened the full 6 GHz band in July 2026. What Wi-Fi 7 changes for hotels, restaurants and clubs, what it costs, and when waiting is the better call.

Read article
Managed IT7 min read

Disaster recovery when there are 180 covers booked tonight

Business continuity for hotels and restaurants with covers booked tonight. RTO and RPO explained, the failure scenarios that happen and what restores service.

Read article
Compliance7 min read

PCI DSS for restaurants and hotel groups: the practical checklist

A practical PCI DSS checklist for multi-site restaurants and hotels: who enforces it, scope reduction, segmentation, phone orders and v4.x deadlines.

Read article
Cyber Security7 min read

Hospitality cyber security: the attack paths that actually get used

The attack paths actually used against hotel and restaurant groups, the defences that work, and what to do in the first hour of a suspected incident.

Read article
Compliance7 min read

Martyn's Law for venues: what it requires, and where technology helps

What Martyn's Law means for hospitality operators: the standard and enhanced tiers, the SIA's role, and where technology genuinely supports the duties.

Read article
Managed IT7 min read

Microsoft 365 when most of your workforce never sits at a desk

How to licence Microsoft 365 across hotel and restaurant teams, covering frontline worker tiers, shared device sign-in, identity, offboarding and backup.

Read article
Managed IT7 min read

Windows 10 end of support: the estate you cannot see

Windows 10 support ended in October 2025 and ESU Year 1 expires this October. A practical refresh plan for back-office, EPOS-adjacent and AV control PCs.

Read article

Put this into practice

Services and sectors this touches

Secure, scalable and seamless IT wherever hospitality takes you.